A worker in an orange high-visibility suit climbs a flare support structure against a clear blue sky. The structure is painted orange, matching the worker's attire, and is equipped with safety railings and platforms. The worker is secured with safety harnesses and ropes, indicating adherence to strict safety protocols. The photograph is taken from ground level, looking up and emphasising the structure's height and scale within the expansive sky's expansive backdrop.

NRA Guy Wire Replacement

The North Rankin Complex (NRC) Facility is located offshore of the Northwest Shelf of Australia and processes gas for transfer to the Karratha Gas Plant. The facility is made up of the North Rankin A & B Platforms (NRA & NRB) and has a Flare Bridge that supports the Flare Stack, High Pressure (HP), and Low Pressure (LP) piping. Personnel were only allowed on the flare stack when the flare was offline due to the risk of flare heat radiation. The guy wires on the Flare Stack were overdue for replacement, and a mobile crane could not be used for the work due to equipment unavailability.

Background

The North Rankin Complex (NRC) Facility, comprising the North Rankin A & B Platforms (NRA & NRB), is located offshore of the Northwest Shelf of Australia at a nominal water depth of 124.3m. It processes gas for transfer to the Karratha Gas Plant.

NRA has an 184m long Flare Bridge, which supports the Flare Stack, High Pressure (HP), and Low Pressure (LP) piping to the flare stack, along with met-ocean instrumentation, radar, and flare knockout drums. The Flare Stack supports the HP and LP flare tips and is supported by eight guy wires. The complete flare assembly is approximately 36m high.

Due to the risk associated with flare heat radiation, personnel are only allowed on the flare stack when the flare is offline. Further, due to the flare stack’s corrosion of the platforms and stairways, rope access was to be used when working on the flare stack.

The guy wires are typically replaced every 10-15 years, but the current guy wires have been in service past this period. The last guy wire replacement was completed in 2006, with the work scope completed using a mobile crane mounted on a trolley that, in turn, was mounted on a pair of crane rails that run along the top of the flare bridge. The mobile trolley used then was no longer available, and the crane rails were no longer suitable for mounting a similar-sized trolley on the crane rails.

Phase 1: Guy Wire Replacement Study

An offshore oil platform is illuminated against the twilight sky. The sprawling structure is a complex of pipes, towers, and equipment extending into the sea. A prominent flare structure rises on the right, mirrored by the bridge connecting the platform to the smaller structures on the left. The sky transitions from warm sunset hues to the deep blue of the approaching night while the calm sea stretches to the horizon, reflecting the last light of day. The image captures the industrial might set against the natural beauty of the ocean at dusk.

Woodside engaged Vertech Group to execute a study to replace the 8-guy wires of the flare tower On North Rankin Alpha using rope access within the 24-day “gas to gas” window of the 2023 turnaround.

The area was to be accessed using Rope Access Techniques, and a scaffold was erected to lay down areas and temporary barriers at various working areas.

Phase 2: Project Planning & Engineering

Four industrial workers in bright orange coveralls and white helmets are seated together on a deck, reviewing documents and engaged in a discussion. The sea is visible in the background, suggesting they are on an offshore platform. They are surrounded by various work equipment and safety gear, indicating a break or planning session amidst their tasks. The workers appear focused and involved in their work, highlighting the importance of teamwork and communication in such environments.

Working closely with the Woodside shutdown team and other specialist contractors such as Alliance Engineering, the Vertech project team provided the necessary deliverables, including a baseline project schedule, project execution POB profile an execution schedule, detailed and comprehensive implementation work packs, work method statement(s) for our site teams, an implementation bill of materials, lift Plans, detailed tensioning procedures and Vertech completed an onshore work method trial.

Phase 3: Pre-Shutdown Work

An industrial worker in orange safety gear, including a helmet with a mounted light and hearing protection, works on a vertical structure above the ocean. The worker is harnessed and using a descent control device attached to a rope, indicating rope access work. They appear to be inspecting or repairing a series of pipes on the side of the structure, which is streaked with rust, showing the harsh maritime environment. Below, the blue sea stretches out, emphasising the height at which the worker is operating.

The Guy wire replacement is a complex and critical path task. As such, detailed close visual inspection, load testing and NDT were required once the flare was fully blown down and isolated before the installation of any rigging equipment. Once completed, the team installed all the initial rigging arrangements, inertia reels, rope access equipment, davits, air hoses and pig receivers and established dropped object protection.

It was necessary to complete fabric maintenance on some regions of the flare stack and pilot line pipe support, remove several potentials dropped objects, and then de-rig all materials before moving into the detailed sequence of guy wire replacement and tensioning for each wire.

Phase 4: Guy Wire Replacement

A group of workers in high-visibility orange suits and white helmets are on a metal scaffolding structure high above the ground. The scaffold is supported by a large rusted metal beam that angles upwards, with cables attached for added stability. They are working against an almost cloudless sky, which highlights the height at which they are working. This industrial scene occurs on an offshore oil rig structure requiring elevated construction or maintenance work.

The Guy wire replacement is a complex and critical path task. As such, detailed close visual inspection, load testing and NDT were required once the flare was fully blown down and isolated before the installation of any rigging equipment. Once completed, the team installed all the initial rigging arrangements, inertia reels, rope access equipment, davits, air hoses and pig receivers and established dropped object protection.

It was necessary to complete fabric maintenance on some regions of the flare stack and pilot line pipe support, remove several potentials dropped objects, and then de-rig all materials before moving into the detailed sequence of guy wire replacement and tensioning for each wire.

Client Testimonial

“The scope was completed over a 4-week period involving significant coordination with rigging, scaffolding, and rope access. Not only was the job completed efficiently and without any incident, but the team also found improvements and adapted along the way. An outstanding team effort…”

  • NRA HSEC

Want to know more? Contact us below:

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
A group of industrial workers on an offshore platform pose for a photo. They wear bright orange coveralls, safety helmets, and protective glasses. Most are standing, and some are kneeling, with smiles indicating a moment of camaraderie or completing a job well done. The background features the metal structures of the platform, painted with visible rust, and the ocean extending to the horizon, suggesting a remote and harsh working environment. The clear sky and natural daylight enhance the visibility of the team's features and safety gear.
NRA Guy Wire Replacement Case Study
PDF 416.1 KB